
BioStar and its equipment suppliers have extensive experience in handling and processing dairy manure. Dairy waste is more difficult to process than other waste since it contains high amounts of fiber and a lower concentration of ammonia Ñ making a fertilizer plant more profitable due to the high volumes of waste.


BioStar Renewables is proud to announce the start of construction of an approximately 2 MW solar PV array that will serve clean, renewable electricity to the City of NormanÕs Wastewater Treatment and Wastewater Reclamation Facilities. The City of Norman has established a Net-Zero Emissions goal for city buildings and is aggressively pursuing options to ensure they can meet these bold inspirational goals. The City of Norman is leading the transition to a balanced energy future that relies heavily on renewable resources.

The City of San Bernardino is home to over 217,000 persons while San Bernardino County has a population of approximately 2.2-million people. The amount of food waste generated is significant and has put stress on the traditional methods of disposal such as landfills, composting facilities, and municipal solid waste facilities.
With recent studies indicating that approximately 36-million tons of food waste goes un-utilized and only about 3% of this food waste volume is recovered — the project will prove beneficial in the form of energy, nutrient, and carbon recovery as well as composting. If not, most food will end up in landfills or other disposal methods that provide little to no value to the community.
Developed on a 5.42-acre site, the San Bernardino Waste-to-Energy project goal is to provide a valuable facility for resource recovery, energy production, and financial benefits to the region by utilizing food waste resources as feedstock — producing beneficial products and materials.
The facility accepts pre-consumer food waste and processes the waste to produce several beneficial products and materials — with the development of a food-waste-to-energy digester facility utilizing anaerobic digestion, gas capture and processing, and electricity production from gas-powered generators using the methane-rich biogas.
The facility plans to have two digesters, each with a liquid capacity of approximately 1.8-million gallons and additional space available for the expansion of future digesters, helping to produce approximately 2.6 MW of electrical power using the biogas-powered engines. The exhaust from the engines will be treated to meet strict California air quality standards as well as noise restriction requirements. Heat will be recovered from the engines and recycled to maintain optimum temperatures in the digesters to maximize efficient operational conditions.
Finally, the project will be equipped with a 2.6MW utility grid interconnect. Two (2) 1.3 MW engine generators will be installed and the Project is to be operated to produce enough biogas to fuel the engine generators up to 2.6 MW. The project is supported by a 20-year power purchase agreement with Southern California Edison. The site layout is designed to handle additional feedstocks to further increase volume revenue, while sending excess biogas to heat recovery or to the flare.
While some of the outputs are valuable and have immediate beneficial use, others, such as air emission and effluent to sewer, require additional treatment to meet current air and water standards. The below graphics outline the project’s inputs and outputs.

The purpose of the proposed solar power facility is to supplement the current power generated by Inland Empire Utilities Agency (IEUA) from biogas and to reduce peak loads from Southern California Edison (SCE) with electricity supplied from the solar photovoltaic system. The proposed solar power facility (SPF) is designed to generate up to one (1) megawatt of electricity from the photovoltaic system and the SPF is proposed to be installed on the CCWRF project site. The proposed project consists of installing the SPF panels at one of several open location on the CCWRF site and connecting these panels to the SCE electrical grid which is located adjacent to the project site. All of the above proposed activities will occur within the footprint of existing disturbed areas at the CCWRF site.





18,888 solar panels were installed on this 30-acre site with a flat tracker system to produce 6 MW DC of renewable energy. Additionally, 9,400 total linear feet of medium and DC voltage cabling were installed underground with precise spacing in the trench through the use of prefabricated components. This system is designed to meet the U.S. Air Force Academy’s stringent engineering design standards. This project was funded by the American Recovery and Reinvestment Act of 2009.

Phase I of this design-build project included the installation of 14,612 roof-mounted solar panels on Buildings 20, 56 and 810 at the Denver Federal Center campus. These three roof-top arrays are tied to the existing electrical distribution system. The system is 3.2 MW DC. This project was funded by the American Recovery and Reinvestment Act of 2009.






The 600 kW DC Cactus Garden Solar project consists of 2,112 photovoltaic modules on a 4-acre site and is the largest solar installation by a food manufacturer in Nevada. The Cactus Garden project generates renewable energy for the Ethel M® chocolate facility owned by the Mars Corporation. (Photos courtesy of juwi solar, inc.)

This 300 kW DC, design-build solar project was built at the Fort Carson Army Base. The array is located on several carport structures in the parking lot of a new Military Intelligence Battalion Headquarters building.

2MW distributed generation solar project behind the meter.

This solar project is expected to generate the equivalent of more than 30% of the Navy Air Weapons Station, China Lake's annual energy load. This will help to reduce costs by an estimated $13 million over the next 20 years. Responsibilities included: civil, metal erection, module installation, A/C, D/C, substation tie-in and management services.




Located on 160 acres in eastern Modesto, California, this photovoltaic system will power the equivalent of over 6,000 homes with renewable energy. BioStar and sister company, E Light, completed the electrical, AC, DC, and panel installation for this project.




This project is located on a 72,000 sf, raised seamed roof above a parking garage on the Camp Lejeune Marine Base. Onsite services included: racking installation, D/C, setting AC & DC equipment, module installation, DC array wiring, and DAS & MET Station monitoring and controls. Designed to withstand wind and seismic loads on the existing metal roof, using pre-engineered attachment methods.

This project is the nation's largest on-site solar installation at an end user-owned facility. The 171 acre site includes a ground-mount, single axis tacker installation. The solar photovoltaic system supplies power to a $1 billion dollar existing data center on the site. The scope of work included installation of driven and drilled piers, erection of the single-axis tracking system, PV module installation, SCADA, and all DC and AC electrical work.

This 160-acre project, located near Phoenix, included the installation of 61,920 panels on a ground-mount of an ATI tracker system. BioStar and E Light’s scope of work included module installation, A/C, D/C, and converter tie-in.

This is a 497KW ground mount solar project, which was built on an old gravel pit in Summit County, CO. BioStar and E Light’s responsibilities included module installation and converter tie-in.


The NC PV II Solar project is a 20MWac capacity and 25.05MWdc single-axis ground-mounted Solar Facility connected to Duke Energy. The project is located in Conover, NC, and covers approximately 115 acres. BioStar and E Light provided CM services, DC and MV electrical services, equipment signage, SCADA install, and commissioning of the facility.


This, 26 MW DC, the ground-mount solar project sits on approximately 160 acres outside of Bakersfield, CA. This project utilizes nearly 80,000 – 325 watt modules. E Light completed the electrical portion of this project and BioStar was the installer.



Fort Churchill is a very unique project in Yerington, NV approximately 50 miles southeast of Reno. This project uses mirrors to concentrate the sun’s power to a receiver which harnesses the energy.


Launch Development's project revamped the old Gateway 2000 retail shopping center in Overland Park, KS. In addition to renovating the retail storefront and commercial parking lot, BioStar Renewables provided exterior site lighting for 420 new apartment units.

Regulus, a 472 acre, 60.48 MW DC, is a single axis tracker project outside of Bakersfield, CA. This project utilizes over 248,000 modules. BioStar and E Light completed the electrical portion of this project including the module install electrical DC scope and MV copes of work.

The large room with high ceilings at Aeromotive's new facility required high lumen lights with excellent coverage. The factory LED lighting allows technicians to work with precision without straining to see the fuel system products??_they are building, while saving energy.



The car lot, service bays and parts department at Roberts automotive dealership had poor light coverage with multiple dark spots. BioStar designed a solution that increased light levels and saved energy, even after the addition of several exterior area lights. Lighting costs in the upgraded areas were reduced by 60% due to the combined energy and maintenance savings.



The Piper is a unique luxury assisted living facility that utilizes an innovative design philosophy which provides a home within a home. The design team transforms assisted living into warm, nurturing homes that foster independence. The lighting design helps create this atmosphere and contributes to residents' health and well-being. LED lighting was an essential part of the new construction plans. BioStar provided over 3000 lights for the 100,000 square foot, 120 unit building complex and for the 5 acres of landscaping and parking.

Located in Lemoore, CA Henrietta solar farm is a 127.50 MW solar power plant. Scope included all electrical work and module installation. This project contains a new version of Oasis 3 Tracking System with improvements to the DC cable tray and larger 2 MW blocks.


Claremont is a 21.92 MW project located in Claremont, NC. The project included a difficult off-site overhead medium voltage line to the substation at 35 KV.

The Boonybrooke Solar Farm is located in Florence, AZ and covers approximately 282 acres. The project is 50MWac capacity and 62.64MWdc, the power plant is connected to SRP energy. Provided CM services, PV installation, DC and MV electrical services, Equipment Signage, SCADA Install, and Commissioning of the facility. The Solar Plant is a single axis ground-mounted Utility-scale solar project with approximately 144,000 solar panels.

Elm City is a 53.62 MW solar power plant located in North Carolina. This project utilizes First Solar's thin-film module technology mounted on a fixed-tilt racking system. It has a challenging 4-month construction schedule. E Light's scope of work will include all electrical work and module installation.

This multi-phase, 260 megawatt, thin-film, fixed position, solar project is located in Desert Center, California. E Light performed the electrical scope of work on this project. Desert Sunlight Solar Farm provides enough energy to serve the needs of about 160,000 average California homes.

Planet Fitness is dedicated to providing the healthiest and most enjoyable environment for their customers. To meet this goal they realized they needed to increase light levels in their facility. LED lights have been shown to improve people's physical and mental well-being, increasing energy levels because of their similarity to natural sunlight. BioStar was able to provide a cost-effective way to brighten the environment in the gym. Lighting costs were cut in half so the fitness center LED lighting upgrade will pay for itself.

BioStar provided new office and warehouse lighting for Haith & Co. on a tenant improvement project for their tenant, Air General. BioStar replaced 130 warehouse and office fixtures with 114 LED fixtures, which will save more than $60,000 in energy savings over the next 10 years while eliminating lighting maintenance for their tenant.



BioStar Renewables has partnered with Eighteen Capital Group on several turnkey LED lighting projects across their portfolio of multifamily properties. BioStar's team enjoyed brightening up this South Kansas City community near I-435 & State Line Road.


BioStar Renewables provided a turnkey LED lighting retrofit for Central Farm Supply in Kentucky. Substantial energy savings and a dramatic improvement in quality of light made this project a success.






BioStar installed 223 LED high bay fixtures as a part of a tenant improvement project for SF Spice's new facility in California.


The Alameda Towers Condos LED lighting upgrade greatly improved the color and coverage of light in the garage, while at the same time reducing the building's lighting bill by nearly 165,000 kWh annually, for a payback period of 1.4 years.

Being a busy hotel, a flexible installation schedule was very important to Holiday Inn. BioStar worked with the manager to coordinate a plan for retrofitting the entire hotel. The upgrades were completed in stages to ensure that it did not interfere with guests' experience or bookings.

U.S. Toy improved the quality of light in their office while achieving a 64% energy savings. Their project earned them an award from the Department of Energy's Better Buildings Challenge Interior Lighting Campaign.
BioStar upgraded over 450 LED lights in a weekend without disrupting business. Employees were amazed to see the difference in light color and quality when they returned! BioStar Lighting's flexible installation schedule combined with the fast and clean 1-minute installation of Orion Energy Systems LDR Troffer Retrofit lights make lighting upgrades easy for any business.
Pleased with the retrofit of their offices, US Toy continued the lighting upgrades in their warehouse. By choosing a variety of warehouse LED lighting fixtures to meet their needs, the building now uses nearly 70% less energy, with an annual savings of 256,000 KWH, and an investment payback of less than 2 years.
The energy savings as well as the improvement in lighting color and brightness are remarkable when upgrading metal halide or high pressure sodium lamps. In the before photo, the contrast is significant between the daylight entering the building and the metal halide lamps. After the installation, the warehouse LED lights match the lighting color temperature of natural light.

Block & Co. began upgrading the lighting in their portfolio of commercial properties with the complete retrofit of the Landing Mall. BioStar replaced over 300 fixtures and over 1,500 lamps in the center court, hallways, parking lots and Tres Bliss store with energy efficient LEDs. Timers and dual switching add control and energy savings.

When Grace Church began the expansion of their building, they knew they wanted their new facilities to have a modern and welcoming ambience. Recognizing that high-quality LED lighting design would help fulfill this goal, they employed BioStar's team in designing lighting solutions tailored to each space. The result is an elegantly modern church that guests delight in visiting. In addition to a modern look and feel, Grace Church also wanted an energy efficiency solution that would both benefit the environment and reward them with financial savings. They discovered that LED lighting would significantly reduce energy use with a relatively small increase in their construction costs. The church will save approximately $476,000 on outdoor lighting costs alone.

BioStar Renewables worked with Block & Co. to upgrade the LED lighting throughout all common areas, offices and the parking garage in this iconic Plaza building. Block & Co. has been aggressive in achieving sustainability and energy related goals across their portfolio, working on several projects with the BioStar team to improve their tenant's space while saving energy and money.
A leader in commercial real estate service and innovation, Block & Company Inc. has established an initiative to save energy and money across their portfolio of properties. Searching for energy efficiency solutions that make economic sense, they partnered with BioStar and completed LED projects at the Skelly Building, The Landing Mall, Summit Woods pads and Summit Crossing.
At the Skelly Building on the Country Club Plaza, home of Block & Company Inc.'s headquarters, the LED upgrade of more than 1100 fixtures achieved 71% energy reduction, saving almost 300,000 kilowatt-hours per year. Including maintenance savings, the retrofit reduces total lighting costs by 75%, resulting in a 1.9-year payback after a rebate from KCP&L.


MC Realty is a leader in commercial building efficiency, especially in downtown Kansas City. MC Realty has done more than just promote energy efficiency, they have implemented energy efficiency aggressively in their buildings. BioStar and MC Realty have partnered on nine LED lighting projects, mainly retrofitting parking garages and stairwells. Notable projects include the garage at the Marriott Downtown and the Broadway Square Building.



BACK TO PORTFOLIO







Rooftop-mounted Photovoltaic systems totaling 1.85MWdc on four Colorado Target Stores. The stores are located in Arvada, Aurora, Edgewater and Englewood Colorado. These SunPower projects are part of Target’s initiative to put solar on 200 of their stores.

The Sulphur Springs Solar project is a 22.97 MW solar photovoltaic generation facility located in Cochise, AZ. The projects site is approximately 130 acres. Three of the nine blocks that complete the facility utilize a new proprietary voltage limiting device. It allows a 25% increase in modules per string, reducing the number of DC strings per MW of Solar.

The Victory Solar Project is a 15.90 MW project just north of Bennet, CO in Adams County. This project is situated on 160 acres. Notable structures on the site include a substation, an airport beacon, and overhead power lines. E Light installed the PV Modules in addition to the electrical work on this project.

E Light was responsible for all AC, DC, grounding, control wiring, module installation and wire management on this 25.37 MW tracker project. We also performed the lay out and conduit installation of 11 PCS inverter pads along with setting and connecting all equipment. This project utilized an above ground cable tray system for routing DC and control cabling that connected through an in ground concrete vault to the equipment pad. The medium voltage cables, however were all underground.

Bison Solar is a 36.31 MW photovoltaic electricity-generated facility located adjacent to the Rawhide Energy Plant, spanning nearly 250 acres north of Wellington, Colorado. BioStar installed PV modules and the electrical.

The Lamesa Solar Project is 100MWac capacity and 130.5MWdc single-axis ground mounted Solar Facility. The project is located in Lamesa, TX and covers approximately 887 acres in Dawson County. The project includes over 410,000 polycrystalline solar panels with BioStar's oversight of CM services, DC and MV electrical services, equipment signage, SCADA install, and commissioning of the facility.

When the property manager at Cargo Largo learned of the benefits of LED lighting, he decided that replacing their energy efficient fluorescent lighting would resolve several issues. The motivation to upgrade came from not only the energy savings, but also the improved light in the warehouses full of inventory, the ability to resolve lighting design issues, and the elimination of bulb replacement.


BioStar Renewables worked with Block and Co. to upgrade the LED lighting on the exterior of this retail shopping center in Lee's Summit, MO. This project is providing energy savings and operational cost savings related to lighting maintenance, but perhaps most importantly, it is providing a safer environment for patrons of the shops.

Locarno Plaza offers contemporary luxury living, so top-quality LED lighting that matches the old world charm makes sense both economically and aesthetically. BioStar upgraded the lighting in the common areas including the lobby, hallways, parking garage, elevators, offices, as well as exterior landscape and security lighting. Between energy savings and replacement bulbs, the project will save an estimated 180,000 kWh annually, resulting in a project payback of 1.8 years! Additionally, the time saved allows maintenance to focus on other upgrades and repairs.

In 2015, Tutera Group began retrofitting fluorescent and metal halide fixtures throughout their senior living and commercial real estate portfolio. Highland benefitted from an interior and exterior commercial LED lighting upgrade consisting of more than 300 fixtures. The turnkey installation resulted in a zero-maintenance solution and more than 210,000 kWh saved annually.

BioStar Renewables was selected to upgrade the exterior and shop lighting at this premier dealership in Charlotte. BioStar has been proud to partner with Hendrick Automotive on several subsequent projects as they continue to address energy efficiency and wuality of light across their dealerships.


In 2015, Tutera Group began retrofitting fluorescent and metal halide fixtures throughout their senior living and commercial real estate portfolio. Plaza Manor benefitted from an interior and exterior commercial LED lighting upgrade, consisting of 400 fixtures. The turnkey installation resulted in a zero-maintenance solution and more than 110,000 kWh saved annually.

BioStar's LED lighting design team helped design and procure lighting for this new construction project in Chanute, KS. Tech Industries, now called Orizon Aerostructures, provides complex subassemblies for the aerospace industry.

BioStar Renewables has partnered with The Tutera Group's commercial real estate team to upgrade this building as a part of a large renovation of the asset. BioStar helped bring the design team's vision to life with bright, long-lasting, energy efficient lighting. BioStar provided design and photometric support, as well as supplied the entire fixture package for the remodel.

In addition to upgrading their portfolio of senior living communities and commercial real estate properties, Tutera Group retrofitted their Kansas City headquarters with advanced LED lighting. The project received an award in exemplary commercial real estate and the hospitality sector from the Department of Energy's Better Buildings Challenge Interior Lighting Campaign. The award recognized outstanding performance in BioStar's application of high efficiency troffer lighting systems and Tutera Group's commitment to energy reduction. More than 600 lights were retrofitted, reducing the building's lighting energy use by 62% and saving over 100,000 kWh of electricity per year.

Tutera Group, a commercial real estate and senior living management company updated 13 of their properties with turnkey LED retrofits.
BioStar was selected to perform the lighting design and fixture procurement for The Tutera Group's Memory Care expansion at their Carnegie Village Senior Living Community and to help bring their vision for this amazing facility to life. BioStar had previously retrofitted the existing facility to energy efficient LED decorative and commercial fixtures and were hired a second time to upgrade more than 800 lights which resulted in estimated energy savings of 335,000 kilowatt-hours, with a two year payback.
Research has shown that LED lighting has positive effects on health including reduction in age-related disorders, headaches and vision loss, making LEDs ideal for senior living communities.

BioStar Renewables worked with a partner, Navitas, to complete a district-wide LED lighting upgrade for Lockwood, including their largest facility, the high school. The students in the district will benefit from an enhanced learning environment, while the district benefits from operational savings.

BioStar Renewables has partnered with MC Realty Group to tackle a variety of projects in this landmark building in downtown Kansas City. A very busy building with significant foot traffic for extended hours, lighting is of utmost importance, which is why BioStar and MC Realty teamed up to retrofit comon area downlights, reccessed tracks and troffers with long-lasting, energy efficient LEDs that will pay for themselves ten times over.

BioStar Renewables worked with Eighteen Capital Group to upgrade the lighting at this apartment community in Texas. Improving the light levels around the community, as well as achieving operational savings were the main goals, both of which were achieved in this successful project. BioStar provides on-going warranty support to Eighteen Capital Group across a variety of projects in which BioStar has previously provided turnkey services.

BioStar has supplied energy efficient lighting to all 16 of Basis' new school builds from California to New York since 2012. At first, the architect on the jobs specified traditional lighting. Eventually, he saw that on average, each school is able to save about $25,000/year from reduced energy consumption, and a further $7,000/year in maintenance savings through avoided bulb and ballast replacement. The LED lights use 60-65% less energy. Now the architect understands that energy efficient lighting in schools is a smart choice, and specs LED lights in all new builds. BioStar supplies the whole lighting package, right down to the exit signs.

BioStar worked with NFI Management to update their properties across the KC metro with energy efficient LED lighting. BioStar was able to capture significant rebate dollars from the Evergy energy efficiency rebate program, and achieve a fast project payback. The properties will benefit from significant energy and maintenacne savings, as well as improved security and safety for years to come.

BioStar Renewables implemented a community-wide LED lighting retrofit project to improve light levels around the exterior and common areas of this apartment community in Gladstone. Energy and maintenance savings, combined with a safer, brighter environment made this project a success.


BioStar Renewables upgraded a variety of exterior fixtures including wall packs, flood lights, and decorative lighting to improve the light levels across this vast apartment community in the heart of the KC metro.

BioStar Renewables worked in conjunction with our partner, Navitas, to complete a district-wide LED lighting upgrade for Lockwood School District. By retrofitting fluorescent fixtures with energy efficient LED lamps and fixtures, BioStar helped the school district achieve their energy savings goals and improve the learning environment district wide.

One of the premier senior living communities in the Kansas City area, Tiffany Springs provides luxury residences and first-in-class care for Kansas City's seniors in the Northland. BioStar is extremely proud to have partnered on yet another fantastic project with the Tutera Group, a leading provider in Kansas City and across the country. BioStar provided lighting design services and procured all of the fixtures and lighting controls throughout the facility. It was a pleasure to help the Tutera Group design team execute their vision for this community.

An iconic part of the Northern skyline, the State Street building is now the home to the United States Department of Agriculture. BioStar Renewables partnered with MC Realty Group, a first-in-class, facility operations provider in Kansas City, to replace the old metal halide parking fixtures with energy efficient LEDs that reduced lighting operating costs more than 90%.

BioStar Renewables worked with Golden Boy to provide LED lighting upgrades in their store.

Launch Development's project revamped the old Gateway 2000 retail shopping center in Overland Park, KS. In addition to renovating the retail storefront and commercial parking lot, BioStar Renewables provided exterior site lighting for 420 new apartment units.

Mission Chateau opened for business the Spring of 2018 in Prairie Village, Kansas. BioStar Renewables procured the lighting package for The Tutera Group's newest, state-of-the-art assisted living community. The Tutera Group has been committed to sustainability, working with BioStar on 15+ LED lighting retrofit and new construction projects over the past three years. From custom chandeliers to back-of-the-house LED strips and troffers, Mission Chateau is 100% equipped with LED lighting, providing a bright, healthy community for seniors in Kansas City.

The Antonito II Solar Project is 1,200KWac capacity and 1,500kWdc Single Axis Tracker Solar Facility. The project is located near Antonito, CO and covers approximately 12 acres in Conejos County. The project will have 4,760 solar panels. Provided CM services, DC and MV electrical services, pile and racking installation, equipment signage, perimeter fence, civil work, SCADA install, and commissioning of the facility.

The APS Paloma Solar Project is a 886kWdc fixed tilt ground mounted Solar Facility. The project is located in Gila Bend, AZ and covers approximately 8 acres. This project is an addition to the original Paloma project and contains 8,440 thin film solar modules. Provided construction management services, DC and MV electrical, pile and racking installation, equipment signage, SCADA install, and commissioning of the facility.

BioStar Renewables was selected to replace the metal halide fixtures in the parking garage at this iconic hotel which has been a feature of the Kansas City skyline for decades. Using energy efficient LED fixtures and enhanced photometric design, the BioStar team was able to drastically improve the light levels in the garage, all while generating big savings for our customer. The fixtures utilize built-in infrared sensors to maximize savings by slightly dimming and conserving energy during times with no foot or vehicle traffic. BioStar has been partnered with several projects at the Kansas City Marriott Downtown related to energy efficiency and building optimization.
BioStar Renewables was proud to be invited back to the Marriott Downtown Kansas City to help tackle an interior lighting project primarily consisting of ""back of the house"" lighting, stairwells and more. Many of the fixtures replaced or retrofitted are operational 24/7, which created substantial energy savings and a fast payback. The hotel was able to further utilize Evergy's energy efficiency rebate program to help pay for the project.

Curtis Wagner Plastics selected BioStar Renewables to retrofit and replace their lighting with energy efficient LED lamps and fixtures. As a manufacturing business, lighhting was important and the upgrade was well recevied from the production floor. Beyond better quality of light, C.W. Plastics will benefit from substantial energy savings and reduction in lighting maintenance.

Hallmark worked with BioStar to retrofit parking garages, starting with the very prominent Crown Center garage. They wanted a new aesthetic that would reflect the design of the new Halls store. The resulting transformation has received extremely positive responses regarding the light output, aesthetics, and energy efficiency. Hallmark is so pleased with the new lights that they have decided to retrofit nearby parking garages.

BioStar Renewables helped Zion Lutheran Church upgrade their fluorescent and inadescent lighting to LED, improving the quality of light in the church while eliminating lighting maintenance and creating significant energy savings!

BioStar provided the development, engineering, procurement, and construction (EPC) services, as well as ongoing operations and maintenance (O&M) and asset management services. California based contractor, Spectrum Energy Development Inc. played a pivotal role in site installation activities and services. The project created jobs for about 30 people at construction peak and can be looked at as an impetus for other solar research projects in California and helping to drive down the cost of solar energy.


Penetrating Roof Mounted, Fixed Tilt System

Situated on 16 acres approximately 4 miles southwest of Temecula, CA sits the Santa Margarita Ecological Reserve (SMER) Research 1 Solar project, which serves the City of Temecula and Lake Elsinore with clean, renewable energy. The 3.7 MWdc project, which is powered by more than 10,000 photovoltaic (PV) modules, will displace over 4.5 metric tons of carbon dioxide equivalent emissions per year, the equivalent of taking 971 cars off the road annually. The cities will purchase the clean energy generated by the solar farm to reduce the cost of power from the local utility company by approximately 15%.
In addition to the public benefits of lower electricity rates and obtaining electricity from a renewable source of power, SMER Research 1 and San Diego State University have agreed to conduct substantial academic research projects at the solar power generating facility site that will study solar radiation, solar energy, soils, and other meteorological and geotechnical data as well as habitat and habitat restoration after the contract ends.
BioStar provided the development, engineering, procurement, and construction (EPC) services, as well as ongoing operations and maintenance (O&M) and asset management services. California based contractor, Spectrum Energy Development Inc. played a pivotal role in site installation activities and services. The project created jobs for about 30 people at construction peak and can be looked at as an impetus for other solar research projects in California and helping to drive down the cost of solar energy.

BioStar acquired, owned and operated this New Jersey solar PV array from a project partner as a result of an exit. Our asset mangement team led customer communication, including monthly and quarterly production updates to ensure BioStar was meeting our requirements under the previously negotiated PPA. BioStar has since sold the portfolio in which this project resides.

Pennsauken School District Solar project completed construction and commenced operation in October of 2018. The project consisted of Solar PV, totaling 4MWdc, and roof replacements on 8 School buildings plus the Administrative Building in the Pennsauken School District. This project will generate over 4,500,000 kWh annually across all 9 properties for the next 25 years reducing the School DistrictÕs reliance on utility provided electricity.

In mid-2017, BioStar Organics, LLC formed a partnership with Perfect Blend, an Organic Fertilizer manufacturer and distributor located in Othello, WA to install and operate a facility that produces BioStarÕs Super Six 6-0-0 Liquid Organic Fertilizer Ñ utilizing BioStarÕs patented technology. The facility will produce approximately 500,000 gallons of produce annually and has contracted to see all of the production for the next five years.